February 20: Finish design work for database
February 27: Being able to recieve and put data from the web
to the database
March 13: Have all of my web pages created and able to read,
write, update and delete.
March 27: Have the Forms Authenication working.
April 3: Start making the web pages visually appealing.
April 10: Have the project done, so that I can begin testing
and error checking.