Timeline
1/24/07: Receive capstone
project.
-1/31/07
(week 1): Meet
with project leads. Come to an understanding on definition of
project. Webpage must be up and running with a journal page,
project requirements page, philosophy section and resume.
-2/07/07
(week 2): Learn
about web-based systems and define what the scope of the project will
be... include the scope, framework, and development strategy of the
system in system proposal report. Timeline on webpage is due.
-2/14/07
(week 3): Create database. Create rough user interface for
application.
-2/21/07
(week 4): Create further functionality for application behind the user
interface. Insert test data into database.
-2/28/07
(week 5): Start creating communication functionality between
application and database.
-3/07/07
(week 6): Further develop application. Start learning about
web functionality.
-3/14/07
(week 7): Halfway
point.
At this point, a local demo of the application must be
finished.
-3/21/07
(week 8): Spring
break.
-3/28/07
(week 9): Explore and add web functionality to application.
-4/04/07
(week 10): Finalize web communication functionality.
-4/11/07
(week 11): Easter
break.
Make sure application looks professional and add any
unforeseen utilities.
-4/18/07
(week 12): Finalize all aspects of application and database.
-4/21/07
(week 13): Debug!
-4/28/07
(week 14):
Finalize published website. Polish any rough areas, make sure
there are no errors. Work on presentation.
-End of
semester (week 15): Project completed. Binder and application
are due.