Plan
Updated February 18, 2009
There are eight major aspects to the project which are scheduled.
- Project management
- Web site
- Celebration of Student and Faculty/Staff Collaboration
- Hardware - revision 1
- Hardware - revision 2
- Software components
- Presentations (walkthrough and final)
- Graded/Dated Milestones
While I haven't used project planning or Gantt chart software before, I did some reading and put together what I believe to be a fairly complete description of tasks, subtasks, and scheduling. As I move on in the project, and as I figure out how to better model the task relationships in my project, I'll be updating this page. Click to open just the Gantt chart in a new window, or view the full export from my project planning software. These links open in a new window because they do not currently provide links back to this page.