| 02/17/2024 | Working with all three rotors ✔ | 
| 02/24/2024 | Setting selection and storage implemented ✔ | 
| 04/08/2024 | Translate c++ code to c# ✔ | 
| 04/12/2024 | Have machine interface finished ✔ | 
| 03/12/2024 | Project website outlined ✔ | 
| 04/19/2024 | Project website completed ✔ | 
| 04/24/2024 | Presentation complete ✔ | 
| 05/06/2024 | Documentation complete ✔ | 
| 02/20/2024 | List of supplies compiled ✔ | 
| 02/27/2024 | 3d parts modeled (inital) ✔ | 
| 03/08/2024 | Physical design complelty drawn and scaled (models finalized) ✔ | 
| 03/12/2024 | Breadboard researched (plan of attack organized) ✔ | 
| 03/12/2024 | Motors researched (plan of attack organized) ✔ | 
| 03/22/2024 | Parts printed ✔ | 
| 04/05/2024 | Mach 1 assembled✔ |